• Completion Date: 16-11-2010
  • client: GENERAL DIRECTORATE OF INFRASTRUCTURE INVESTMENTS ANKARA
  • Name of Work:
    Surveying, Design and Engineering Services of Implementation Projects of Bandırma-Bursa-Ayazma-Osmaneli; Ayazma-İnönü Railway (High Speed Train Project Services) and Feasibility Studies

BANDIRMA AYAZMA

146.3 km 250 km/hr high speed railway line between Bandırma – Bursa – Ayazma – Osmaneli, 3 stations, 156 culverts, 86 underpasses, 8 overpasses, 36 bridges and viaducts (8.810,00 m) as well as 19 cut-and-cover tunnels (3.737,00 m), 20 tunnels (23.910,00 m), Mapping, expropriation plans, soil investigation works, architectural-statics-electrical-mechanical, Superstructure, Electrification, Signalization and Telecommunication, EIA Report, Feasibility Studies, Cost Estimations and Quantity Studies and Preparation of Tender Files and Digital Simulations.

Related Works